be2 = 750 mm
beff = b0 + be1 + be2 = 0 + 750 + 750 = 1500 mm
α = 1 (≥4.0 → α=1.0)
PRd1 = 0.8·fu·π·d²/4 / γV = 81.66 kN (shank)
PRd2 = 0.29·α·d²·√(fck·Ecm) / γV = 83.13 kN (concrete)
PRd = min(PRd1, PRd2) = 81.66 kN [governs: shank (eq.6.18)]
Fc,full = 0.85·fck/γc·beff·hc = 3060 kN
Nc,full = min(Fa, Fc,full) = 2999.8 kN
PNA: PNA in slab
Mpl,Rd (full, η=1) = 783.48 kNm
N studs per half = 37 → total = 74
η actual = 0.572 (ηmin = 0.49) → OK
Mpl,Rd (η=0.572) = 491.35 kNm
nL = n0·(1+1.1·φt) = 6.4·(1+1.1·2.5) = 23.98
δG (long-term) = 1.47 mm
δQ (live) = 0.91 mm
δshrink = 1.25 mm
δtotal = 3.64 mm
Limit L/250 = 32 mm → PASS